David Mancini & Sons, Inc.

Riverland Stormwater Improvements

Project No. P13086 · Fortify Lauderdale · Phase 1

Timeline

Construction schedule

Supplied East Melrose exhibit

Riverland construction remains pending City approval and notice to proceed. The exhibit dates below are not a confirmed street-by-street Riverland schedule.

Original schedule PDF

Section durations

Estimated work periods, listed by section—not a sequential construction calendar.

  • Section 1

    4weeks

    November 9 · Listed start*

    16 structures · 1,300 ft of pipe

  • Section 2

    6weeks

    Start date unconfirmed

    22 structures · 1,900 ft of pipe

  • Section 3

    8weeks

    Start date unconfirmed

    Approximately 27 structures · 2,350 ft of road

  • Section 5

    3weeks

    Start date unconfirmed

    1,500 ft of road

*Section 1 lists November 9 without a year. No completion date or additional section start dates have been supplied.

Planning & needed-by dates

These dates are planning requirements, not confirmed construction starts.

  1. December 1, 2026

    Section 7

    Final plans needed

  2. December 7, 2026

    Section 4

    Flow model determination and plans needed

  3. December 7, 2026

    Section 5

    Section needed by this date; construction start unconfirmed

  4. January 15, 2027

    Section 6

    Final plans needed

Timing still unconfirmed

Sections 4, 6, 7 have no construction start or duration listed. Planning deadlines do not establish when crews will begin work.