Timeline
Construction schedule
Supplied East Melrose exhibit
Riverland construction remains pending City approval and notice to proceed. The exhibit dates below are not a confirmed street-by-street Riverland schedule.
Section durations
Estimated work periods, listed by section—not a sequential construction calendar.
Section 1
4weeks
November 9 · Listed start*
16 structures · 1,300 ft of pipe
Section 2
6weeks
Start date unconfirmed
22 structures · 1,900 ft of pipe
Section 3
8weeks
Start date unconfirmed
Approximately 27 structures · 2,350 ft of road
Section 5
3weeks
Start date unconfirmed
1,500 ft of road
*Section 1 lists November 9 without a year. No completion date or additional section start dates have been supplied.
Planning & needed-by dates
These dates are planning requirements, not confirmed construction starts.
December 1, 2026
Section 7
Final plans needed
December 7, 2026
Section 4
Flow model determination and plans needed
December 7, 2026
Section 5
Section needed by this date; construction start unconfirmed
January 15, 2027
Section 6
Final plans needed
Timing still unconfirmed
Sections 4, 6, 7 have no construction start or duration listed. Planning deadlines do not establish when crews will begin work.