Riverland Stormwater Improvements

Proposed construction: pending City approval, approximately two years once work begins

North
W Broward Boulevard
South
Davie Boulevard
West
Riverland Road
East
SW 21st Avenue / I-95

Riverland neighborhood

Project limits & location

City of Fort Lauderdale · Project No. P13086

Original limits PDF
North limit
W Broward Boulevard
South limit
Davie Boulevard
West limit
Riverland Road
East limit
SW 21st Avenue / I-95
Riverland project limits: W Broward Boulevard to the north, Davie Boulevard to the south, Riverland Road to the west and SW 21st Avenue / I-95 to the east, outlined on an aerial map
Red dashed outline: project limits. Location reference only; not to scale.Open full-size limits map

Highlighted work areas

Section map & timeframes

Supplied East Melrose exhibit · Proposed section timing. Green highlights show the work areas on each sheet.

Original PDF

Section 1

4weeks

November 9 start*

16 structures · 1,300 ft of pipe

Section 2

6weeks

Start date unconfirmed

22 structures · 1,900 ft of pipe

Section 3

8weeks

Start date unconfirmed

Approximately 27 structures · 2,350 ft of road

Section 5

3weeks

Start date unconfirmed

1,500 ft of road

*The exhibit lists November 9 without a year. Durations are estimates, not a confirmed week-by-week sequence; construction remains subject to City approval and notice to proceed.

East Melrose exhibit C004 · Section 1, with work sections highlighted in green and timing annotations
C004 · Section 1Open full-size map

Section 1

4 weeks estimated construction · November 9 start*

16 structures · 1,300 ft of pipe

Planning deadlines

These are plan-needed or section-needed dates in the exhibit, not confirmed construction starts.

Section 7
December 1, 2026
Final plans needed
Section 4
December 7, 2026
Flow model determination and plans needed
Section 5
December 7, 2026
Section needed by this date; construction start unconfirmed
Section 6
January 15, 2027
Final plans needed

01

Project purpose

Riverland has no comprehensive stormwater system. During moderate to heavy rainfall, water collects on streets and properties because there is nowhere for it to drain. This project will install a drainage system that collects stormwater and carries it out of the neighborhood.

$79.6M

Contract value for the Riverland improvements, awarded to David Mancini & Sons by the City of Fort Lauderdale.

~2 years

Estimated construction duration, measured from the second notice to proceed to substantial completion.

02

Scope of work

Drainage pipes and structures

New storm drains and underground pipes on Riverland streets to collect stormwater and carry it away from homes and roads.

Pump stations and force mains

New stormwater pump stations and force mains that move collected stormwater out of the neighborhood.

Exfiltration and water quality structures

Trenches and structures that let treated stormwater soak back into the ground instead of ponding on streets.

Water and sewer line relocation

Water and sewer lines that conflict with the new drainage system will be relocated.

Restoration

Roadways, driveways and swales dug up for the work will be restored once construction is complete.

This project is part of Fortify Lauderdale, Phase 1 of the City's Stormwater Master Plan.

03

What residents can expect

Have a question or concern about the work? Report an issue or browse the FAQ.